Sunday, November 20, 2011

October 2011: Filling the trench and opening the stormwater pipe

At the beginning of October we were still battling to find rubble to fill the trench. Soon after that, we received loads from many different people.Once it had been dumped, our workers used wheelbarrows to move it along the trench. 


It took an amazing amount of rubble but eventually it was finished.
Our pipes were still draining so the "industrial drain" was working well.


At the end of the trench and at the top of the embankment was  a one meter square brick hole. Further down the embankment we  found and unblocked this pipe.


We then realized we had opened an old storm water drainage system.Runoff from Standard Drive flowed under the school in the bricked tunnel and out through this pipe.


 Out came many years of rubbish which we removed...

And voila -- a new shallow dam!
The old wall needed repairing, so that has been done too.
Now all we need is more rain to keep it full!

Friday, September 2, 2011

August 2011 Top dam -- taking the papyrus out and draining the lane

AUGUST 2011

 Top Dam  
 The island of papyrus was blocking the outlet at the spillway


John Barrow of Barrow Constructions  generously loaned us a TLB for the day.


Moses, the driver, dragged the island slowly to the edge


 A huge heap of papyrus being pushed up the bank


The last little bit!!


The spillway is clear again


The papyrus on the bank where it will dry


Our lovely dam!!



August 2011 Draining the lane below the school

 August  2011 

 After we had finished removing the papyrus from the top dam we moved to the  muddy lane below the school


First  the fallen tree had to be removed


The first "bite"of the trench
  

Within two hours the trench had filled with water
 from the countless springs


Now the pipes had to be laid under the path


The first of three pipes went in


 and the water started draining into the stand of poplar trees


The final job was to flatten and compact the soil to make a road


     All done --  a big improvement!
     The trench will be filled with large rubble and will continue to drain
 the water out.


Enjoy!!

Monday, April 25, 2011

April 2011

April 2011

The bridge at top dam was destroyed after a huge storm. Logs floating in the dam were swept over the wall and crashed into the bridge

                                                
The workers set to cleaning up the mess


A few hours later a smaller but serviceable bridge was in place.

These plants were hanging over the spillway


And a short time later it had all been cleaned up


We moved along the wall to the unruly bamboo


And that too was removed


The piles of logs lying in the river and grass were moved to one place


They were heavy!


But the guys never complained


The last task was to remove the tree that was blocking the path  on the dam wall


10 minutes with a chain saw.......


All gone!!




Autumn leaves in Delta Park




Enjoy the Park, it's looking lovely at the moment with it's autumn finery!

Saturday, March 12, 2011

March 8th 2011 Hyacinth top dam and draining the lane below the school

 At the beginning of March we noticed hyacinth  flourishing at the inlet of the top dam. It had to come out!!

                                       

The boat bringing in a load while the weed is thrown onto plastic sheeting


Alan's big fork worked well


Lunchtime and it is looking much better


Hurrah! All gone!!


And that is what we took out!!



Peter at work. In the lane, a trench on the left was dug revealing five springs
Under the walling is a 6m x10cm pipe draining the water to the other side.


A second pipe was put in further down the lane where there were a couple more springs


It should dry out now and hopefully we can walk through with dry feet!

20th February 2011 Draining the quagmired lane below the school.

Work was needed on the lane below the school. As we had more rain so the lane became muddier. We dug channels and they started draining well. There are 4 natural springs , this one was running like a fully opened tap.


 More channels  busy draining the area


The "path" below the school! The bridge has been temporarily disassembled to dig a ditch underneath it.



The channel flowing well under the "bridge"


Monday, January 31, 2011

(5) Jan 2011 Fixing the dam wall at 3rd dam


January 2011

 Peter Hammond volunteered to fix the leaking dam wall

A coffer-dam was built from rocks
Clay soil was stamped down making it watertight


 The hole was cleaned out


15 wheelbarrows of cement were mixed


It was packed into the hole, and along the whole bottom area of the wall


Finished! Within three days the water had covered  the coffer-dam and the dam filling up.
Great job!!